House-bank source and DC distribution

← Electrical configuration · Equipment Register · Circuit Register

Owner-confirmed installation facts, not an independently electrically tested as-built schematic. The complete house bank is deliberately represented by one aggregate two-terminal source EQ-059. Its internal batteries, chemistry, capacity and forthcoming LiFePO4 upgrade belong in a separate audit.

Positive supply and common negative return

House-bank source — six DC service circuits ANL and battery-post fuses owner-confirmed fitted; one common switch for House/Autopilot/Windlass; 70 A windlass breaker retained; fuse mapping untraced
Aggregated 12 V source — internal battery composition deferred EQ-059 — House bank — aggregate source port
Positive distribution · battery-post and ANL fuses fitted; ratings unverified BB-003 — Positive distribution with owner-confirmed installed ANL fusing
Always supplied These feeds bypass SW-002
Watchkeeper DC-WAT-01 Always supplied; installed ANL fuse scheme reported, specific terminal/rating not traced Protection way/rating not yet mapped
Pump 1 DC-BIL-01 Bypasses SW-002; individual fuse location and rating not traced Protection way/rating not yet mapped
Pump 2 DC-BIL-02 Bypasses SW-002; individual fuse location and rating not traced Protection way/rating not yet mapped
Common remotely switched supply One switch controls three services
SW-002 — Common House + Autopilot + Windlass remote switch One physical switching function owner-confirmed; 2025 photo shows WhisperPower family, model label unverified
House DC-HOU-01 Common SW-002 control; specific fitted ANL fuse allocation not traced Protection way/rating not yet mapped
Autopilot DC-PIL-01 Common SW-002 control; specific fitted ANL fuse allocation not traced Protection way/rating not yet mapped
Windlass DC-WIN-01EQ-061 — WindlassEQ-062 — contactorCB-006 · 70 A — breakerDC-WIN-02 — control circuitSW-003 — foredeck controlSW-004 — foredeck control Owner-confirmed Lewmar HX1 800 W; 70 A CB-006, separate contactor EQ-062 and two foredeck controls; ANL rating/way untraced Protection way/rating not yet mapped

Common battery-negative return / BMV measurement

Battery negative → BB-004 tinned-copper interconnect → EQ-060 Victron BMV-712 shunt → BB-001 system negative distribution (link to confirm).

Only battery-negative interconnect on shunt battery side; all load and charger returns on shunt system side.

Six functional services: three bypass the common switch; House, Autopilot and Windlass switch together. ANL and battery-post fuses were fitted per owner, and Windlass retains a 70 A breaker. Fuse way/rating allocations remain untraced. The photographed 2025 switch is WhisperPower branded, while the currently fitted product code and downstream wiring are not verified.

The house-bank positive source supplies BB-003. One physical remote battery switch SW-002 controls House, Autopilot and Windlass together; Watchkeeper, Pump 1 and Pump 2 bypass it.

SupplyRemote-switch stateCircuitAs-fitted protective evidence
WatchkeeperUnswitchedDC-WAT-01ANL fuse installation confirmed as a group; actual current way/rating untraced
Pump 1UnswitchedDC-BIL-01Protection device/branch position not yet reconciled
Pump 2UnswitchedDC-BIL-02Protection device/branch position not yet reconciled
HouseSwitched through SW-002DC-HOU-01Owner confirms original ANL fuse installation; current assignment untraced
AutopilotSwitched through same SW-002DC-PIL-01Individual downstream fuse allocation untraced
WindlassSwitched through same SW-002DC-WIN-01 → Lewmar HX1 EQ-061Fitted 70 A breaker CB-006, with fitted ANL fusing also confirmed; circuit order/rating of ANL not traced

There are six distinct functional circuits, three unswitched and three controlled by one common remote switch. The six circuits are not assumed to correspond to six individual terminals or fuseholders on the source busbar.

Owner-confirmed fitted protection — ANL, battery posts and windlass breaker

The owner has now explicitly confirmed that all of the ANL fuses and battery-post fuses associated with the earlier DC-distribution build were fitted, and the windlass’s existing 70 A circuit breaker was retained in its supply. Therefore installed ANL/MRBF fusing is a fact, not merely a project proposal. Exact fitted ratings, fuse counts, cable sizes, and today’s connection to each service circuit still need inspection.

The older sources record the following historical nominal design ratings, which must not be mistaken for a current fuse-body reading:

Design recordNominal ratings and allocations documented thenStatus
July 2025 house-bank discussionTwo 125 A MRBF battery-post fuses with equal 25 mm² feed cables; an intermediate design also considered 80 A MIDI/MEGA panel, 40 A MIDI/MEGA pump and individual 20 A pump fusesBattery-post fuses confirmed installed; old exact ratings, count and MIDI/MEGA alternatives not independently checked
5 August 2025 DC Distribution Panel Upgrade80 A ANL Primary, 80 A ANL Auxiliary, 100 A ANL Windlass, 40 A ANL Watchkeeper; proposed Windlass 25 mm², 10 m, Lewmar HX1Original ANL fuses confirmed installed; the 2025 functional group names and per-fuse ratings must not automatically be mapped to today’s six service circuits
Current owner confirmation70 A windlass breaker retained in the windlass supplyConfirmed fitted protective device CB-006, in addition to the installed ANL fuse arrangement

A 100 A ANL fuse and 70 A breaker can both exist in the same windlass supply. They may perform different upstream-cable protection and local isolation functions. Their actual ordering and protection selectivity remain unverified. We are not choosing one in place of the other.

Current windlass identity: Owner confirms fitted Lewmar HX1 800 W, EQ-061, 70 A CB-006 breaker, and a separate contactor EQ-062 controlled by two foredeck switches SW-003 and SW-004. The earlier 80 A breaker reference was an audit error, superseded 1 November 2026. The historic 100 A ANL remains a design rating pending inspection of the actual fuse. Contactor maker/part, UP/DOWN mapping and any control fuse are unverified.

Evidence provenance: Owner’s direct installation confirmations in the October 2026 electrical audit, plus 2025 dated planning records. The physical 5 August 2025 photograph shows one WhisperPower-branded remote battery switch and four lower covered fuseholders; the labels and output cables cannot be read. It supports the hardware-family history, not individual fuse allocations. A later BEP 701-MD preference was a replacement proposal, not confirmed installed.

Individual FU-NNN IDs for the source ANL/MRBF fuses will be allocated when we can distinguish the particular fitted devices and identify their physical way/relationship without guessing. This does not defer recording that their installation was owner-confirmed.

Victron BMV-712 negative measurement path

The owner confirms the house-bank negative terminals directly connect through bespoke DIY tinned-copper link BB-004 to the battery-facing terminal of the fitted BMV-712 shunt, EQ-060.

All outgoing house services, windlass return (where connected to this bank), and charging returns must use the system/load side of the shunt to ensure net-bank current measurement. The physical path between this system-side terminal and the existing main negative bus BB-001 remains untraced.

The earlier copper-link design included approximately 25.4 × 3.2 mm tinned copper, but the installed bar’s dimensions and ampacity have not been measured. The BMV fused positive-sense feed and its physical location likewise remain to be inspected.

Remaining as-fitted audit

Trace the battery-post fuse quantity and markings without expanding the aggregate house-bank model; read ANL fuse ratings and identify the photographed fuseholder ways; confirm SW-002’s actual model and common switched output; trace the electrical placement of CB-006 (mounted aft in the engine drive compartment, beneath the aft cabin bunk) relative to the Windlass ANL fuse and its motor controller; then map individual House, Autopilot, Watchkeeper and pump protections and all negative returns.

Safety: This documentation is not an instruction to disconnect live battery cables. Isolate and follow safe manufacturer-approved work methods when conducting the high-current physical survey.